Last updated: November 12, 2026. This article explains how these laws work in general. It isn’t legal advice. Check your state’s statute for the exact rules.
In Indiana, a building department has 7 business days to finish a residential plan review once an application is complete. In Washington, some land use permits get 170 days.
Both are called shot clocks.
The name comes from basketball, and the idea is the same: act within a set time, or something happens. However, what that something is varies a lot from state to state. So does nearly everything else about these laws. If you work in a building department, the details matter more than the name.
This guide breaks a permit shot clock into the 4 parts every law has to define, using real examples from 9 states.
What is a permit shot clock?
A permit shot clock is a law that gives a government a set amount of time to act on an application, with a consequence if it doesn’t. Some cities also set their own review targets. Those matter too, but this article covers state laws, because those carry penalties.
Shot clocks have spread quickly. Georgia, Indiana, Arizona and California all added or changed theirs in 2025 or 2026. Tennessee’s takes effect January 1, 2027.
The 4 parts of every shot clock
Read any shot clock law and you’ll find answers to the same 4 questions. Once you know them for your state, you know how your clock works.
1. What’s on the clock?
Some laws time building permits. Others time land use or development review, and leave building permits alone.
- Building permits: Florida, Indiana, North Carolina and Texas all set deadlines on building permit or plan review.
- Land use and development review: Washington’s 2023 law covers “project permits,” which are land use reviews. Tennessee’s Public Chapter 1044 covers development applications, site inspections and surety releases. It says outright that it doesn’t apply to building, fire, mechanical, plumbing or electrical permits (CTAS).
A department can be on one clock, both, or neither. Start here.
2. When does the clock start?
Not always at submission. Many clocks, especially in newer laws, start when an application is complete. Some older laws count from the day it’s filed, such as Pennsylvania’s (34 Pa. Code § 403.63) and Massachusetts’s (780 CMR 105.3).
Where the clock waits for a complete application, the completeness check matters, and many states now put it on a clock of its own. Florida gives local governments 5 business days to tell an applicant in writing what’s missing. If they don’t, the application is “automatically deemed or determined to be properly completed and accepted” (Fla. Stat. 553.792). Georgia’s SB 447 uses the same 5 business days and the same default (HousingWire). Indiana, for example, gives 3 business days (Indiana HEA 1005).
In practice, an incomplete application that slips through intake can start the clock anyway.
3. When does the clock pause?
Most laws stop the clock while the application is back with the applicant. Lawyers call this tolling.
Arizona’s 2025 law suspends the timeframe from the day a department sends a corrections request until it gets the corrections back (Arizona House summary of SB 1353). Washington leaves out time spent waiting for information the government asked for (MRSC).
Pause rules get less attention than deadlines, but they decide whose time counts. Days with the applicant usually don’t. On the other hand, days with any part of the department usually do. North Carolina’s state fire marshal has said its 15-business-day residential review deadline doesn’t wait while other departments, such as environmental health or erosion control, finish their own reviews (NC Office of State Fire Marshal).
4. What happens when the clock runs out?
This is where states differ most. There are 5 main types of consequence:
| Consequence | How it works | Examples |
|---|---|---|
| Fee cut or refund | The department loses part or all of the permit fee | Florida, Georgia, Washington, Arizona |
| Third-party review | The applicant can have a qualified outside reviewer do the work | Texas, California, Arizona, Indiana |
| Permit must be issued | The department has to issue the permit, or a limited one | Indiana |
| Approved as submitted | The application is treated as approved | Tennessee (development review), California (state agency housing reviews) |
| Court order | The applicant can ask a court to make the government act | Georgia |
Here’s what each looks like in practice.
Fee cuts and refunds
Florida gives local governments 30 business days to review most residential permits and smaller projects, and 60 for larger ones. Miss the deadline and the department “must reduce the building permit fee by 10 percent for each business day that it fails to meet the deadline.” There are exceptions: a written extension, a delay caused by the applicant, or circumstances outside anyone’s control (Fla. Stat. 553.792). In Georgia, a jurisdiction that misses a deadline on a complete application must refund all permit fees (Thompson Hine). Similarly, Washington may require a refund of 10–20% of review fees when its timelines are missed (MRSC).
Third-party review
In Texas, under HB 14, if a city or county hasn’t acted on a plat, plan or permit application by the 15th day after its deadline, the applicant can use a qualified third-party reviewer, such as a licensed engineer. The city can’t charge a fee for that review (Texas House bill analysis). California’s AB 253 lets applicants for small residential projects, up to 10 units, hire a licensed private plan checker if the city can’t finish plan check within 30 days. The city then has 10 business days to act on that report (City of San Diego; Burke, Williams & Sorensen).
Permit must be issued
Indiana goes furthest for building permits. For one- and two-family homes and townhomes, if a department misses its 7-business-day plan review deadline, it “shall issue a permit or a limited permit” by the next business day (Indiana HEA 1005).
Approved as submitted
Starting January 1, 2027, a Tennessee local government that misses its deadline on a covered development application sees it automatically approved as submitted (CTAS). In California, AB 301 does the same for certain state agency reviews of housing permits (Kassouni Law).
Court order
Georgia also lets an applicant ask a court for mandamus, an order requiring the jurisdiction to act, and gives those cases priority (Thompson Hine).
A newer rule: limits on rounds of corrections
Several recent laws limit how many times a department can send an application back. This gets less attention than the deadlines. It may matter just as much.
- Tennessee allows no more than 2 written deficiency notices per development application. After the second, staff must deny it with a 50% fee refund, approve it with conditions, or forward it for a decision (CTAS).
- Arizona allows 1 comprehensive corrections request. Follow-up requests can only cover issues that are still unresolved (Arizona House summary).
- Georgia bars new questions or challenges after a second submission (HousingWire).
Because of rules like these, the first review has to catch everything. An application that arrives missing a form, or with a site plan that doesn’t match the application, uses up a round on something that isn’t a code question.
What this means for your department
You can’t change your state’s law. Still, you can know it well and run your process around it.
- Know your start trigger. Find out exactly what makes an application “complete” under your law, and whether your department has a deadline to say so.
- Treat the completeness check as its own deadline. In Florida and Georgia, a missed completeness notice can start the review clock on an incomplete file.
- Track days with staff and days with the applicant separately. Most pause rules depend on this split, and it shows where your time actually goes.
- Write complete first-round comments. Where the law caps correction rounds, a comment left for the second round may never get one.
Much of the time on any clock goes to applications that weren’t ready when they arrived. We wrote about how departments are fixing that before the clock starts. Click here to read Before the Clock Starts: How AI PreCheck Cuts Correction Cycles.
Free download
Get the shot clock readiness checklist
A 1-page checklist for your team, with space to note your answers. It works whatever your state’s rules are, and covers:
- Knowing your law: what starts, pauses and ends your clock
- Tracking your time and the numbers that matter
- Fixing what arrives before the clock starts
Frequently asked questions
Does the shot clock start when I submit my application?
It depends on the state. Many laws, especially newer ones, start the clock once the application is complete. Some, like Florida’s and Georgia’s, treat an application as complete if the department doesn’t flag missing items within a set number of days. Others, including Pennsylvania’s and Massachusetts’s, count from the day the application is filed.
Do shot clocks apply to building permits or only zoning?
It depends on the state. Florida, Indiana, North Carolina and Texas time building permit or plan review. Washington and Tennessee’s laws cover land use or development review. Tennessee’s law specifically excludes building permits.
Can a permit really be approved automatically?
In some states, for some applications. Tennessee approves covered development applications as submitted when deadlines are missed. Indiana requires departments to issue a building permit, or a limited one, the next business day after a missed plan review deadline. Most of the other laws covered here use fee refunds or third-party review instead.
Does the clock stop during corrections?
In most states, yes. Time while the application is back with the applicant usually doesn’t count. Check your state’s law for exactly when the clock restarts.
How do I find my state’s rules?
Start with your state’s statute or your state building code office. County and municipal associations often publish plain-language summaries, such as MRSC in Washington and CTAS in Tennessee.